12 signs your build in Kenya isn’t where they say it is
Most delays on a Kenyan build have ordinary reasons. If you’re asking how to know your house is really being built, these are the 12 signs worth a calm question, and what to ask for instead.
Last checked:
The 12 signs
Most hold-ups on a self-build have ordinary reasons: rain, a late delivery, a fundi called away upcountry. But if you’re building from the UK, the US or the Gulf, these are the moments worth one more (kind) question, and what to ask for instead of arguing.
Several signs ask you to name the stage you can see in a photo. This is a typical bungalow, stage by stage:
- Foundation
- DPC
- Walls to window height
- Lintel and ring beam
- Roof structure
- Roof sheets
- Plaster
- Fittings and finishes
A storeyed house adds a slab after each floor’s walls.
1The photos are always close-ups
Ask for the same three wide shots every time: from the gate and both front corners.
You notice: a corner, a stack of blocks, a trench, but never the whole building from the road. Ask for the phone to be held sideways, then put this month’s photos next to last month’s.
Words you can borrow: “Can you take the same three photos each time? I want to line them up month by month.”
2The photo and the message don’t match
“We’re at ring beam” but the walls stop below the window tops? Look at the photo before you read the caption, and keep a diary: date, stage told, stage seen.
You notice: you’re told “roofing has started”, but there are no trusses in any photo. Name the stage you see, using the stages above, before you read what you’re told.
Words you can borrow: “Great news! Can you send one wide photo from the road so I can see all of it?”
3A “new” photo looks like an old one
Same clouds, same puddle, same wheelbarrow. Ask for photos as a WhatsApp Document: it keeps the date taken (on a PC: right-click, Properties, Details).
Good to know: Google Lens shows if a picture is already online. Dates can be edited, so a date in the file is a clue, not an answer.
Words you can borrow: “Can you send them as Documents? I want them full size for my folder.”
4There’s never a video, or it always cuts
Ask for a video that opens with a word you chose today and walks in from the gate without stopping.
You notice: only photos. Videos are a few seconds long, start inside or jump between places, and there has been no video call from the site. An old video can’t contain today’s word: the code-word method, step by step.
Words you can borrow: “Can you start the video with ‘mango’ and walk in from the gate? I like feeling I’m there.”
5No sign of work on a weekday
No tools out, dry mixing spot, no fresh mortar. Ask for the weekly labour list: roles, days, daily rate.
Good to know: new blockwork stays darker and damp for a day or so. A labour list is normal paperwork, and nobody’s face needs to be in a photo.
Words you can borrow: “Who was on site this week, and for how many days? It’s for my budget sheet.”
6The site looks like it stopped a while ago
Heavy rust on the column steel, grass in the ballast. Grass takes weeks, not days.
You notice: heavy, flaky rust on the steel sticking out of the columns, grass in the ballast or sand, cement bags gone hard. Ask for one wide photo of the heaps and the column tops. Light surface rust is normal.
Words you can borrow: “Can you send one wide shot of the heaps and column tops, so I know where we are?”
7Material counts don’t add up
Ask for a photo of each delivery with the delivery note in the shot. A block stack is rows × columns × layers.
You notice: “2,000 blocks delivered”, but the stack plus the walls built don’t look like 2,000. Steel should be listed on the note by size (Y10, Y12…).
Words you can borrow: “When the delivery comes, can you snap it with the note on top?”
8Receipts that aren’t receipts
A handwritten list with no hardware name or phone. Ask for the printed receipt (many hardwares now issue KRA eTIMS ones).
You notice: a screenshot of a total, or a receipt that never arrives. A printed receipt or delivery note shows the hardware’s name, phone and date, so you can match it to the delivery photo.
Words you can borrow: “Could the hardware give a printed receipt? I’m keeping everything together.”
9M-Pesa totals don’t match the quote
Keep a one-page ledger: date, amount, the name on the payment, what it was for. Total it stage by stage against the quote or BQ.
You notice: what you’ve sent for a stage adds up to more than its quote, or the money goes to a name you don’t recognise. A column for “receipt yes/no” helps too. (BQ is the bill of quantities.)
Words you can borrow: “Who is [name] on this payment? No problem, I just like my records tidy.”
10Urgent money with no breakdown
“Cement goes up tomorrow.” Ask for the hardware’s written quote and pay its Till directly. A real price rise survives a one-day check.
Good to know: a written quote shows quantity × unit price, with the hardware’s name and phone. When you pay its Till or Paybill directly, the M-Pesa message shows the business name.
Words you can borrow: “Send me the hardware’s quote and Till number. I’ll pay them directly so you don’t carry cash.”
11Rain, again and again
The long and short rains really do stop work. Ask what was done on the dry days, and plan slabs for the drier months together.
You notice: the long rains (March to May) and the short rains (October to December) stop work for real. The sign is labour money asked for while work is stopped, or rain blamed in a dry week. Before you ask, look up that week’s weather for the town.
Words you can borrow: “What can the team do on dry days? Shall we plan the slab for after the rains?”
12Every update comes from one person
That says nothing bad about them; it’s just one view. Every so often, get a second, neutral, up-to-date look.
You notice: every photo, receipt and update comes through one person, and nobody else has seen the site in months. Photos from someone neutral, now and then, take pressure off them too: the photos answer questions, not an argument.
Words you can borrow: “I’m getting a photo record with the date on every photo for my file now and then. Fewer questions for you.”
None of these means anyone has done anything wrong. Make the checks routine from day one and they never feel like an accusation.
Want a second, neutral look at your build? Tell me the town and the stage you’ve been told it has reached.
Chat on WhatsAppHow to ask without starting a fight
Four habits that keep build conversations friendly:
- Make it routine, not a reaction. “I’m keeping a build diary” is easier to hear than “I don’t believe you.”
- Ask, don’t conclude. “Help me understand” opens a conversation. “Why did you lie?” ends one.
- One question per message, and thank them for good updates. A voice note often sounds warmer than a text.
- Keep it private. Don’t post your site, plot details or anyone’s photo in a group to ask “is this right?”
Download the free 2-page PDF
The same 12 signs, with the words you can borrow and the stage ladder, on two pages you can print or forward on WhatsApp. Free to share, unchanged. No sign-up.
Download the checklist (PDF, 94 KB)
There is no form and no list. If you’d like the next guide when it’s written, send me a message on WhatsApp and I’ll send it to you myself.
When does a neutral, up-to-date look help?
When every update comes from one person, or when you’d simply like a record for your file from someone with no stake in the answer. A visit adds a second view without anyone having to feel accused.
Truhali’s construction check records the stage the work has reached, as seen on the day: photos with the date on each one of each part of the work, code-word videos and a plain list, as a PDF within 48 hours. It costs USD 75 (about KES 9,700); the first ten owners pay USD 65 (about KES 8,400): USD 35 when they book, and the rest after they’ve seen the report. It describes what’s visible. It doesn’t approve work or tell you whether to pay anyone.
- Before you send the next building instalment
- If the updates have stopped altogether
- All three prices
- Where visits happen: Nairobi and Kiambu
Visual observation only: not a valuation, survey or certificate.
General information, not legal, financial or construction advice. None of these signs on its own means anyone has done anything wrong, so please don’t use this list to accuse anyone; if you’re worried about how something was built, ask a qualified building professional.
Questions about a build that has slowed
How do I know whether my build is actually behind?
Compare the same spots, not the same promises. Photographs taken from fixed points, week to week, make movement obvious. Photographs from whatever angle looked good that day can hide a month of nothing.
Can I ask for more detail without accusing anyone?
Yes, and the wording matters more than the question. Ask about the thing, never the person: what did the last delivery cover, which part of the work is next, what is holding it. The list on this page is written to be forwarded as it stands.
A second, neutral look at your build.
Message on WhatsApp with the town and the stage you’ve been told it has reached. I reply personally, usually within a few hours (Kenya time).
You pay part when you book, and the rest only after you’ve seen your report. Message, voice note, email or a call: whichever suits you.