Before you send the next instalment
The request always arrives with a reason, and the reason is usually true. This page is what to see before each payment on a build in Kenya, how to pay against stages rather than dates, and how to keep records that help the builder as much as they help you.
Last checked:
The request always comes with a reason
Cement has gone up and the price holds only until tomorrow. A lorry is at the gate and the driver wants paying before he tips. The fundi has four people to pay on Saturday evening. Those reasons are usually true.
The difficulty is the timing. An urgent request is the worst moment to decide anything, because there is no time to look at a photo, open the quote or add up what has already gone out. A genuine price rise, a genuine delivery and a genuine wage bill all survive one day. So the useful move is neither to refuse nor to send at once, but to buy yourself a day.
One sentence does it: “Noted, thank you — I’m sending it tomorrow morning, please send me the hardware’s quote and one wide photo of where the work has reached.” That is not a no. It gives a time, it asks for two ordinary things, and it leaves the fundi able to tell the driver something.
Pay for stages you can see, not dates
A simple bungalow goes up in an order that hardly ever changes, and every step looks different from the one before. That is what makes a stage checkable from a photo, and a date not checkable at all. “At ring beam by the 20th” is a plan. “Here is the ring beam” is something you can look at.
- Foundation. Trenches set out with string lines, footings cast, then stone or blocks up to ground level and the middle filled with hardcore.
- DPC. The damp course at ground level: a black membrane and the first flat surface across the whole footprint, so the shape of the house becomes readable in a wide photo.
- Walls to window height. Blockwork about a metre up, with the openings left out. Easy to judge against a person standing beside it.
- Lintel and ring beam. Concrete bands with steel inside them, over the openings and around the top of the walls. The shuttering is often still on.
- Roof structure. Trusses and purlins up, and the roof outline appears against the sky.
- Roof sheets. Sheets or tiles fixed and the building closed: the biggest visual change of the build.
- Plaster. Walls rendered flat inside and out, so the colour goes from block grey to one even grey.
- Fittings and finishes. Doors, windows, ceiling, tiles, plumbing, electrics, paint. The longest stage, and the one most often paid for twice, because “finishes” covers so much.
A storeyed house adds a slab after each floor’s walls, then starts the wall sequence again on top. Keep the same stage names from the first week, in that order, so “beam level” never means two things.
What to see before each payment
Five things, the same five every time. They take someone on site about ten minutes.
- One wide photo from the same spot as last time, with the whole building in frame, phone held sideways. Two wide photos from one place a month apart say more than twenty close-ups.
- A photo of the stage being claimed, far enough back to show where it sits on the building. A lintel on its own could be anywhere; a lintel with the corner of the house beside it is placed.
- Delivery notes photographed with the materials in the same shot, not separately: the note on top of the block stack, or against the steel, in one picture.
- A short continuous video walking in from the gate to the work, without stopping or cutting. It takes in what a still leaves out: the heaps, the mixing area, what is stacked where.
- A one-line written note of what the money is for. “KES 95,000: cement 60 bags and sand one lorry, for the slab.” One line in WhatsApp is the line you will be glad of in three months.
Counting what arrived
Quantities are the one part of a build you can count from a photograph, so it is worth knowing how.
- Blocks. A stack is rows × columns × layers. Ask for the photo square-on rather than from the corner, and count the layers from the side. A part-layer on top is normal; note it rather than rounding up.
- Steel. It should be listed by size — Y8, Y10, Y12 — and counted as bundles, because that is how it is sold and tied. “20 bars of steel” means little; “12 bundles Y12, 4 bundles Y10” can be counted in the picture.
- Cement. Bags go hard if they sit on damp ground or through rain, so bags on site for weeks are worth a question. Cement bought early to beat a price rise still has to be used before it sets in the bag.
- Sand and ballast. Sold by the lorry, and a heap is hard to judge, so the note with the lorry in the shot is worth more than the heap.
Ask for the hardware’s own printed quote or delivery note, with the shop’s name and phone number on it, rather than a handwritten list or a screenshot of a total. A printed note gives you a number you can ring to ask a simple question about what was supplied. Many hardwares now issue KRA eTIMS receipts, which carry the shop’s details and the date, so they are worth asking for by name.
Would you rather someone independent looked before the money goes? A Truhali construction check is one Saturday visit to the site in Nairobi or Kiambu: photos from fixed points with the date and time on each one, an arrival and a departure video in which I say the code word you sent that Saturday morning, what you were told set beside what I saw, and the visible materials counted, as one PDF within 48 hours. It is USD 75 (about KES 9,700); the first ten owners pay USD 65 (about KES 8,400): USD 35 when they book, and USD 30 after they’ve seen the report.
Chat on WhatsAppPay the hardware directly where you can
Where a supplier has a Till or Paybill number, paying it yourself for materials, and paying labour separately to the person doing the work, keeps the two kinds of spending apart. Materials are a quantity at a price; labour is days at a rate. Mixed into one transfer they are almost impossible to total by stage afterwards. Kept apart, they add up on their own.
This is about clean records, not about doubting anyone. It also takes a weight off the fundi: no cash carried to the hardware, nothing paid out of his own pocket, and no questions later about a total he only passed on. A payment to a registered business shows the business name in the confirmation message, so part of the record writes itself.
Keep a one-page ledger
One sheet, one row per payment, seven columns: date, amount, who it went to, what it was for, stage claimed, stage seen, receipt yes/no. A notebook works. A phone spreadsheet works better, because it adds up.
Then total it stage by stage against the quote or the bill of quantities. That one habit is the most useful thing on this page. It turns a vague feeling that a lot has gone out into an answerable sentence: the quote for the ring beam was KES 310,000, I have sent KES 395,000 against it, and two rows have no receipt.
It also ends most arguments before they start, and as often as not it ends them in the fundi’s favour: prices move, a wall comes out longer than drawn, a stage genuinely costs more than quoted. With a ledger, that is a short conversation about two rows. Without one it is a long conversation about trust, and nobody wins that.
Asking without causing offence
Make this routine from the first instalment, not something that appears in month six. “This is how I keep my build file” is easy to hear. The same request arriving suddenly, after months of money sent on a message alone, sounds like an accusation whatever the words. One ask per message, and thank people for the work.
Holding a request for a dayHi [name], thank you — noted. I’ll send it tomorrow morning my time. Before I do, please send me the hardware’s quote with the quantities on it, and one wide photo from the gate showing where the work has reached. It’s for my build file, so I can tick the stage off. Thanks for pushing the work along.
Asking for the stage photoHi [name], the work is looking good, thank you. For my file, could you send one photo of the ring beam, taken far enough back that I can see the corner of the house beside it? The same spot as last time is perfect. I keep them side by side month by month.
A voice note often lands warmer than a text, and “for my file” explains the request without putting anybody on the spot.
What a photo cannot tell you
Photographs are good at two things: which stage the building has reached, and roughly how much material is on site. They are poor at most of what else matters.
- Workmanship. Whether courses are plumb and level, whether blockwork is properly bonded, whether the plaster will hold. A little shows in a photo; most is judged by hand and eye on site.
- Mix ratios. A photograph of fresh concrete does not say how much cement went into it.
- Steel inside concrete. Once a beam or slab is cast the steel is out of sight, so a photo of it has to be asked for before the pour.
- Whether the design is right. Foundation depth, beam sizes, soil conditions and loadings are engineering questions, not photographic ones.
For any of those, a registered professional is needed on site. The Engineers Board of Kenya keeps a public register at ebk.go.ke, and the National Construction Authority registers contractors at nca.go.ke. A structural visit before a slab is poured costs a fraction of the slab.
Where Truhali fits
Truhali is one person: me, Jose, in Nairobi. Right now I take one kind of visit: a construction check, before you send the next building payment. On a Saturday I go to the site in Nairobi or Kiambu and send photos with the date and time on each one, an arrival and a departure video in which I say the code word you sent that morning, what you were told set beside what I saw, and the visible materials counted, as one PDF within 48 hours. It is USD 75 (about KES 9,700). The first ten owners pay USD 65 (about KES 8,400): USD 35 when they book, and USD 30 after they’ve seen the report. Visits to plots and finished houses are not offered right now.
I never handle building money. I do not pay the hardware, I do not pay the fundi, and I hold nobody’s money on the way through. I also never collect rent, hold keys, find tenants, value land or settle boundaries. I record what can be seen on the day, so the stage in your ledger and the stage on the ground are the same thing.
Visits run in Nairobi and Kiambu on Saturdays. To see what arrives, there is a sample report.
Visual observation only: not a valuation, survey or certificate.
Related
12 signs your build in Kenya isn’t where they say it is is a free checklist of the ordinary moments worth one more question, with words you can borrow for each. The code-word method explains how a word chosen that morning, said at the start of a video, places that video after the moment it was chosen.
Questions about paying the next instalment
How do I know the money went into my build?
You mostly cannot, after the fact, which is why the order matters: pay against a stage you can see rather than a date on a schedule. “Ring beam done” is checkable. “Materials” is not. Where the supplier will take it, pay the hardware directly and keep yourself out of the middle.
He is asking for money before the last stage is finished. What do I say?
Ask about the work, never about him: what the last delivery covered, how many bags, which part of the job it went into, and what is holding the current stage. Those answers are either immediate or they are not, and you have learned something either way without anyone being accused.
See the stage before you send the money.
Message on WhatsApp with the town and the stage you were told the build has reached. I reply personally, usually within a few hours (Kenya time).
You pay part when you book, and the rest only after you’ve seen your report. Message, voice note, email or a call: whichever suits you.